Skip to main content

ALHW to complete Dry Dock Extension project by August 2021




TMI Correspondent
Port Blair, Nov 13: A delegation of the Andaman Nicobar Media Federation (ANMF) has visited the project site of Dry Dock Extension at Marine Dockyard on Nov 9, 2019, where senior officials of ALHW briefed them about the execution of the project.
Earlier, in the conference hall of ALHW, the Deputy Chief Engineer, Andaman Lakshadweep Harbour Works (ALHW), Smt. Mamata Jijith has explained about the Dry Dock Extension project through a power point presentation. Smt. Jijith said, the project "Extension of Dry Dock - II at Marine Dockyard including supply, installation and commissioning of Dry dock pumps and accessories in Port Blair, South Andaman" has been sanctioned by Ministry of Shipping under Central Sector Plan Scheme to the tune of Rs. 96.24 Cr with the stipulated date of completion of 42 months. The project has been awarded to M/s. RDS Project Ltd., Contractor, Port Blair by observing all the codal formalities and the preliminary work commenced at site since 07.03.2017. The scope of work will extend the existing dock by 90 more meters in length to accommodate more vessels and bigger vessels. This facility will double its capacity for ship repair facilities at Port Blair and generate employment opportunities as well as generate huge revenue to the islands. She said that presently 300 employees are working and due to this project 50 more employment will be generated.
The project envisages extension of Existing Dry Dock - II at Marine Dockyard by 90 x 20 x 8.50 mtr founding on RCC Bored piles including providing erecting & commissioning of various type of Mechanical equipments and Electrical installations. Construction of allied structures such as Dewatering pump house, Capstan house, Workshop buildings, Electrical Control room, Generator room, Crane parking shed, Vehicle parking shed, 02 nos. Overhead Tank of its 1.20 Lakhs Ltrs. capacity each at Dockyard I & II and an underground RCC sump of capacity of 1.20 Lakhs Litre. The Andaman Lakshadweep Harbour Works has set a deadline of 2021 for completion of the Dry Dock Extension at Marine Dockyard.
She further informed that, the ALHW has taken up a major project of extension of new dry dock - II at Marine Dockyard to augment existing ship repair facilities at Port Blair. Currently, the piling work of the project is in progress at dock area. In order to boost ship building & ship repairing industry and facilitate the "Make in India" initiative of the Govt. of India., the existing ship repair facilities at Port Blair are being augmented by extending the existing dock length".
In principle, the Ministry of Shipping has approved the proposed RCE for construction of the Extension of Dry Dock-II at Port Blair would be Rs.123.95 Crores which is 28.80% excess over the originally sanctioned cost and the time overrun to implement the extra work would be 24 months i.e. August 2021. After getting the in principle approval from Ministry, the work resumed at site during the month of September-2019. The works is in active progress and try to complete the full scope of the project before the extended targeted schedule of August 2021, the delegation was told.
The Executive Engineer (OS), Mr. P. Ramachandran, Assistant Engineer (Civil) Dry Dock Extn., S. Kasinathan, and Mr. P. Muthaiah, Executive Engineer, ALHW and media team were present on the on the occasion.

Comments

Popular posts from this blog

MP discuses on water projects with Secretary (APWD)

Port Blair, June 16: The Member of Parliament, Shri Kuldeep Rai Sharma, along with the Ex-chairperson PBMC, K Ganeshan today met the Secretary, APWD at his office and discussed major water projects proposed in the islands. He informed the Secretary about the difficulties faced by the residents due to the water crisis Six Municipal Wards, particularly during the dry season. He also requested the Secretary, APWD for completing the repair works of pipelines damaged due to the Dairy Farm Culvert Project. The Secretary, APWD informed the MP that out of the two pipelines damaged at the culvert project site, repair work of one pipeline is already completed and repair work of another pipeline is under progress which will also be completed shortly. Once the work is completed residents will face no water problems. On the culvert project, she informed that work is progressing at a fast pace and is likely to be completed soon. On the proposed major water projects, she informed that the submarine p

One Incoming Passenger arrested with 5.5 KG of Ganja

Port Blair, June 02: Following credible information that one person is coming to Port Blair from Chennai in a fight with huge amount of Ganja, a joint team of PS Chatham and PS Aberdeen was formed headed by SI Shubham Ghosh & SI Mazumder respectively on May 31. The team soon reached ITF Ground and checked the belonging of the passenger, Mr. Ganesh Baag, a resident of Chennai and seized 5.5 KG of Ganja. The operation was carried out under the leadership of SDPO, South Andaman, ASP Kalaivanan R under overall supervision of Mr. Ravi Kumar, SP SA. It is believed that more arrests are possible in this case as Mr. Ganesh is working for a Ganja Racket in Andaman.

Say Good Bye to Plastic Bags - “It is Better for your Generations”

TMI Bureau Port Blair, Oct 02: As part of National Campaign against the single-use plastic and on the occasion of 150th Birth Anniversary of Mahatma Gandhi. Over 25000 cloth bags (made by Skill Development Centre, DBRAIT) were distributed to general public for free by DBRAIT in the Andaman and Nicobar Islands on Oct 02, 2019. At different distribution points, people at large numbers collected the cloth bags in exchange of a polythene bag. Background: Less than 50 years ago plastic bags were a rarity in the world. In Andaman it's just a decade ago Polyethylene were came into use, but badly affected a lot. Before plastic bags, there was paper or cloth. Paper bags worked but they were not easy to carry and they weren't nearly as strong as plastic. The most important part is paper was more expensive to produce than plastic. The cost of disposal and clean up of plastic bags comes back to the tax payer, hazardously. However, polyethylene (the most common type of plast